Here’s link to PART1 https://mps4hana.com/2025/08/21/internal-order-or-project-wbs-part1/
And now let’s look at High-level plan and activities for a scenario /situation : where we require migration steps from Legacy (SAP ECC) to New system (SAP S/4HANA) in which Client was using Internal Orders in ECC and going-forward Client used Project-WBS, instead of Internal Order.
This scenario is common in S/4HANA Greenfield or Selective Data Transition (SDT) projects, where companies move from using Internal Orders for cost tracking to using the Project System (PS) WBS structure in S/4HANA.
🔹 Migration Steps: ECC (IO) → S/4HANA (PS-WBS)
1. Preparation Phase
- Identify scope: Which Internal Orders (open & historical) need to be migrated?
- Classify:
- Active IOs → To be converted into WBS elements.
- Closed IOs → Archived (no migration needed).
- Mapping:
- IO Master Data (Responsible CCtr, Profit Center, Settlement Rules, Status) → WBS attributes.
- IO Categories (Overhead, Investment, Accrual, etc.) → PS object type (Project Definition / WBS).
- Freeze new IO creation in ECC at cutover date.
2. Master Data Migration
- Extract Internal Orders from ECC (
SE16N / AUFK, COAS). - Define Target WBS hierarchy in S/4HANA:
- Create Project Definitions (CJ20N / LTMC / BAPI_PROJECT_MAINTAIN).
- Create WBS elements mirroring IO structure.
- Map IO numbers to WBS codes (store mapping in conversion table for audit).
3. Open Commitments Migration
- Extract open PRs/POs against IOs in ECC.
- In S/4HANA, recreate PR/PO referencing WBS.
- Ensure Purchase Orders reference new WBS element instead of IO.
- Tools: LTMC for MM migration, or custom BAPI programs.
4. Actual Costs Migration
- Historical Costs (Optional):
- Extract historical postings (BKPF/BSEG + COEP).
- Load into S/4HANA WBS via FI journal entries (BAPI_ACC_DOCUMENT_POST) with WBS reference.
- Open Balances (Mandatory):
- Post migration journal entry:
Dr Expense A/c (WBS) Cr Expense A/c (Technical clearing, IO reference) - This clears IO balances and assigns them to WBS.
- Post migration journal entry:
- Repostings: If parallel systems run during cutover, use KB11N / BAPI_ACC_PRIMARY_COSTS_POST to repost open costs.
5. Settlements / Capitalization (if relevant)
- If IOs were used for Asset Under Construction (AUC):
- Run final settlement in ECC (KO88).
- Migrate resulting AUC balances to WBS/Investment Projects in S/4HANA (via CJ88 in new system).
6. Validation
- Compare balances:
- ECC IO report → KOB1, S_ALR_87012993
- S/4HANA WBS report → CJI3, S_ALR_87013558
- Ensure totals match for costs, commitments, revenues.
- Reconcile with Trial Balance to ensure financial correctness.
7. Closing Legacy IOs
- In ECC, mark IOs as:
- CLSD (Closed)
- DLFL (Deletion Flag)
- Ensure no future postings.
8. Post-Go-Live
- Redirect all derivations:
- OKB9, substitution/validation rules → WBS instead of IO.
- Train business users to use PS reports instead of IO reports.
- Archive old IO data if required.
🔹 High-Level Cutover Plan
| Phase | Key Activities | Responsible |
|---|---|---|
| T-4 Weeks | Freeze new IO creation, mapping IO → WBS | Finance/CO |
| T-3 Weeks | Extract IO master data, create Projects/WBS | PS/IT |
| T-2 Weeks | Migrate commitments (PR/PO) | MM/Finance |
| T-1 Week | Dry run: Repost sample costs | Finance/IT |
| Cutover Weekend | Final cost transfer, final settlement, IO closure | Finance |
| T+1 Week | Validation & reconciliation | Finance/Business |
✅ Net effect: After cutover, all future postings go to WBS in S/4HANA, while IOs are frozen and only retained for historical reference in ECC.