Internal Orders or Project-WBS ? – Part2

Here’s link to PART1 https://mps4hana.com/2025/08/21/internal-order-or-project-wbs-part1/

And now let’s look at High-level plan and activities for a scenario /situation : where we require migration steps from Legacy (SAP ECC) to New system (SAP S/4HANA) in which Client was using Internal Orders in ECC and going-forward Client used Project-WBS, instead of Internal Order.

This scenario is common in S/4HANA Greenfield or Selective Data Transition (SDT) projects, where companies move from using Internal Orders for cost tracking to using the Project System (PS) WBS structure in S/4HANA.


🔹 Migration Steps: ECC (IO) → S/4HANA (PS-WBS)

1. Preparation Phase

  • Identify scope: Which Internal Orders (open & historical) need to be migrated?
  • Classify:
    • Active IOs → To be converted into WBS elements.
    • Closed IOs → Archived (no migration needed).
  • Mapping:
    • IO Master Data (Responsible CCtr, Profit Center, Settlement Rules, Status) → WBS attributes.
    • IO Categories (Overhead, Investment, Accrual, etc.) → PS object type (Project Definition / WBS).
  • Freeze new IO creation in ECC at cutover date.

2. Master Data Migration

  • Extract Internal Orders from ECC (SE16N / AUFK, COAS).
  • Define Target WBS hierarchy in S/4HANA:
    • Create Project Definitions (CJ20N / LTMC / BAPI_PROJECT_MAINTAIN).
    • Create WBS elements mirroring IO structure.
  • Map IO numbers to WBS codes (store mapping in conversion table for audit).

3. Open Commitments Migration

  • Extract open PRs/POs against IOs in ECC.
  • In S/4HANA, recreate PR/PO referencing WBS.
  • Ensure Purchase Orders reference new WBS element instead of IO.
    • Tools: LTMC for MM migration, or custom BAPI programs.

4. Actual Costs Migration

  • Historical Costs (Optional):
    • Extract historical postings (BKPF/BSEG + COEP).
    • Load into S/4HANA WBS via FI journal entries (BAPI_ACC_DOCUMENT_POST) with WBS reference.
  • Open Balances (Mandatory):
    • Post migration journal entry: Dr Expense A/c (WBS) Cr Expense A/c (Technical clearing, IO reference)
    • This clears IO balances and assigns them to WBS.
  • Repostings: If parallel systems run during cutover, use KB11N / BAPI_ACC_PRIMARY_COSTS_POST to repost open costs.

5. Settlements / Capitalization (if relevant)

  • If IOs were used for Asset Under Construction (AUC):
    • Run final settlement in ECC (KO88).
    • Migrate resulting AUC balances to WBS/Investment Projects in S/4HANA (via CJ88 in new system).

6. Validation

  • Compare balances:
    • ECC IO report → KOB1, S_ALR_87012993
    • S/4HANA WBS report → CJI3, S_ALR_87013558
    • Ensure totals match for costs, commitments, revenues.
  • Reconcile with Trial Balance to ensure financial correctness.

7. Closing Legacy IOs

  • In ECC, mark IOs as:
    • CLSD (Closed)
    • DLFL (Deletion Flag)
    • Ensure no future postings.

8. Post-Go-Live

  • Redirect all derivations:
    • OKB9, substitution/validation rules → WBS instead of IO.
  • Train business users to use PS reports instead of IO reports.
  • Archive old IO data if required.

🔹 High-Level Cutover Plan

PhaseKey ActivitiesResponsible
T-4 WeeksFreeze new IO creation, mapping IO → WBSFinance/CO
T-3 WeeksExtract IO master data, create Projects/WBSPS/IT
T-2 WeeksMigrate commitments (PR/PO)MM/Finance
T-1 WeekDry run: Repost sample costsFinance/IT
Cutover WeekendFinal cost transfer, final settlement, IO closureFinance
T+1 WeekValidation & reconciliationFinance/Business

✅ Net effect: After cutover, all future postings go to WBS in S/4HANA, while IOs are frozen and only retained for historical reference in ECC.